Author:  TheMews [ Wed May 11, 2011 3:46 pm ]
Post subject:  Gas HWS Compliance (as required by regulator)

The property has been inspected by the statge regulator (WA Gas Networks / Energy Safety).

As a result of this inspection rectification works are required in several areas.
Attachment:
20110509_WAGas_Inspection01.jpg
20110509_WAGas_Inspection01.jpg [ 191.76 KiB | Viewed 8440 times ]
Attachment:
20110509_WAGas_Inspection02.jpg
20110509_WAGas_Inspection02.jpg [ 371.4 KiB | Viewed 8440 times ]


Attachments:
WAGasNetworks_147CharlesStSurveyData.pdf [36.85 KiB]
Downloaded 466 times

Author:  TheMews [ Thu May 19, 2011 3:16 pm ]
Post subject:  Re: Gas HWS Compliance - Duct Doors

Rear buildings only: Vents in duct doors have been increased as required.

Author:  TheMews [ Mon Jun 13, 2011 7:33 am ]
Post subject:  Re: Gas HWS Compliance - Duct Doors

Front buildings only: Vents in duct doors have been increased as required.

All duct doors have now been modified as required.

Author:  TheMews [ Thu Jul 07, 2011 2:05 pm ]
Post subject:  Re: Gas HWS Compliance - Proposed Flueing Solution

Proposed flue solution to support 3 instantaneous gas heaters per duct.

Option 1 - Single Flue (maximum section size 200mm)

Option 2 - Double Flue (maximum section size 150mm)

Attachments:
mews_ducting.jpg
mews_ducting.jpg [ 71 KiB | Viewed 8407 times ]

Author:  TheMews [ Wed Nov 28, 2012 9:58 pm ]
Post subject:  Re: Gas HWS Compliance - 38% Complete

Progress: 38% Complete

Units 01/19/37 Completed Nov 2011 (1 x ARP)
Units 02/20/38 Completed Nov 2011 (1 x ARP)
Units 04/22/40 Completed July 2012
Units 08/26/44 Completed Nov 2011 (2 x ARP)
Units 11/29/47 Completed Oct 2011 (2 X ARP)
Units 13/31/49 Completed July 2012
Units 17/35/53 Completed Sep 2012

Units 03/21/39 to be done Oct 2012 (1 x ARP) need approval to replace electric in 21 (leave capped off flue connection for future)
Units 05/23/41 to be done Oct 2012 (1 x ARP) still awaiting approval from ownerof5 (leave capped off flue connection for future)
Units 07/25/43 to be done Dec 2012 (1 x ARP)
Units 12/30/48 to be done Dec 2012 (1 x ARP)
Units 14/32/50 to be done Dec 2012 (1 x ARP) owner14 and 32 now agree to replace as doing others(inv to exclusive)
Units 16/34/52 to be done Dec 2012 (1 x ARP)52 added to ARP list

Units 06/24/42 scheduled for 2013
Units 09/27/45 scheduled for 2013
Units 10/28/46 scheduled for 2013
Units 15/33/51 scheduled for 2013
Units 18/36/54 scheduled for 2013

Author:  TheMews [ Tue Jan 15, 2013 2:30 pm ]
Post subject:  Re: Gas HWS Compliance - 44% complete

Progress: 44% Complete

Units 01/19/37 Completed Nov 2012
Units 02/20/38 Completed Nov 2012
Units 04/22/40 Completed July 2012
Units 05/23/41 Completed Dec 2012
Units 08/26/44 Completed Nov 2012
Units 11/29/47 Completed Oct 2012
Units 13/31/49 Completed July 2012
Units 17/35/53 Completed Sep 2012

Units 03/21/39 scheduled for 2013
Units 06/24/42 scheduled for 2013
Units 07/25/43 scheduled for 2013
Units 09/27/45 scheduled for 2013
Units 10/28/46 scheduled for 2013
Units 12/30/48 scheduled for 2013
Units 14/32/50 scheduled for 2013
Units 15/33/51 scheduled for 2013
Units 16/34/52 scheduled for 2013
Units 18/36/54 scheduled for 2013

Author:  TheMews [ Fri Mar 15, 2013 2:08 pm ]
Post subject:  Re: Gas HWS Compliance - 77% complete

Progress: 77% Complete

Units 01/19/37 Completed Nov 2012
Units 02/20/38 Completed Nov 2012
Units 03/21/39 Completed Jan 2013
Units 04/22/40 Completed July 2012
Units 05/23/41 Completed Dec 2012
Units 06/24/42 Completed Feb 2013
Units 07/25/43 Completed Jan 2013
Units 08/26/44 Completed Nov 2012
Units 09/27/45 Completed Mar 2013
Units 11/29/47 Completed Oct 2012
Units 12/30/48 Completed Jan 2013
Units 13/31/49 Completed July 2012
Units 16/34/52 Completed Feb 2013
Units 17/35/53 Completed Sep 2012

Units 10/28/46 scheduled for 2013
Units 14/32/50 scheduled for 2013
Units 15/33/51 scheduled for 2013
Units 18/36/54 scheduled for 2013

Author:  TheMews [ Tue Jun 18, 2013 11:03 am ]
Post subject:  Re: Gas HWS Compliance - 83% complete

Progress: 83% Complete

Units 01/19/37 Completed Nov 2012
Units 02/20/38 Completed Nov 2012
Units 03/21/39 Completed Jan 2013
Units 04/22/40 Completed July 2012
Units 05/23/41 Completed Dec 2012
Units 06/24/42 Completed Feb 2013
Units 07/25/43 Completed Jan 2013
Units 08/26/44 Completed Nov 2012
Units 09/27/45 Completed Mar 2013
Units 11/29/47 Completed Oct 2012
Units 12/30/48 Completed Jan 2013
Units 13/31/49 Completed Jul 2012
Units 15/33/51 Completed Apr 2013
Units 16/34/52 Completed Feb 2013
Units 17/35/53 Completed Sep 2012

Units 10/28/46 scheduled for 2013
Units 14/32/50 scheduled for 2013
Units 18/36/54 scheduled for 2013

Author:  TheMews [ Thu Aug 08, 2013 11:35 am ]
Post subject:  Re: Gas HWS Compliance - 100% Complete

Progress: 100% Complete

Units 01/19/37 Completed Nov 2012
Units 02/20/38 Completed Nov 2012
Units 03/21/39 Completed Jan 2013
Units 04/22/40 Completed July 2012
Units 05/23/41 Completed Dec 2012
Units 06/24/42 Completed Feb 2013
Units 07/25/43 Completed Jan 2013
Units 08/26/44 Completed Nov 2012
Units 09/27/45 Completed Mar 2013
Units 10/28/46 Completed Jul 2013
Units 11/29/47 Completed Oct 2012
Units 12/30/48 Completed Jan 2013
Units 13/31/49 Completed Jul 2012
Units 14/32/50 Completed Jul 2013
Units 15/33/51 Completed Apr 2013
Units 16/34/52 Completed Feb 2013
Units 17/35/53 Completed Sep 2012
Units 18/36/54 Completed June 2013