As part of continuing efforts to better secure the complex works will start shortly to close 2 of the pedestrian entry points.
Entry points to be closed:
- Charles Street South Entrance (with stairs)
- Visitor Car Park - Centre Entry
Tasks to be completed (Charles Street South Entrance)
- Fencing around the front steps will be removed.
- Brick steps will be removed and a wall constructed that lines up and is level with the current retaining wall facing Charles Street.
- A new fencing panel will be installed so the fence continues over the new retaining wall section.
- After mortar has dried sufficiently (1-2 weeks) the wall will be backfilled and the garden extended over the area.
Tasks to be completed (Visitor Car Park - Centre Entry)
- Gate will be removed and replaced with a fencing panel cut to fit.
Further information on security improvements is available here:
/viewtopic.php?t=960