Over the coming months a new letterbox system will be installed on the fence line in the area next to the north pedestrian gate.

The following tasks will need to be completed:
  • Removal of the brick sign.
  • Preparation of the area.
  • Installation of new letterbox system.
  • Installation of new fencing around letterboxes.
  • Concreting of area around new letterboxes.
  • Removal and cleanup of old letterbox area.
Attachments
20140408_155012.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

23/04/2014 : Brick sign was removed.

/viewtopic.php?t=764
Attachments
20140423_091555.jpg
20140423_135654.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

05/05/2014 : Over 5 tonnes of soil was removed from the area to allow the section against the fence to be close to street level.

Unfortunately works had to be stopped as a large tree stump was discovered under the ground level.
Attachments
20140504_093253.jpg
20140504_093253.jpg (100.83 KiB) Viewed 45114 times
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

10/05/2014 : Soil and many of the roots were cleared from around the stump to allow it to be cut out.
Attachments
20140510_142209.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

17/05/2014 : Tree stump was removed and taken to the tip. Note that the tree stump and root system weighed over 1.2 tonnes when dumped at the tip.
Attachments
20140517_172923.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

26/05/2014 : Re-leveling of area has been completed.
Attachments
20140527 155619.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

28/05/2014 : Letterbox system has been ordered (lead time is 4-8 weeks)

Letterboxes will be Clear Anodised (as we are concerned about graffiti)
Numbering Strips will be black with light (off-white) lettering.
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

Hi All,

It is will sadness that I relay the following:

Simon, the representative that had been assisting with this project passed away in mid June this year.

I have been speaking to Simon regarding this project for a number of years and I believe it was a surprise to everyone when he passed.

Our thoughts are with his wife Anna and family.

Unfortunately this has delayed the project somewhat and we are now working out when installation can take place.

Saxon
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

Installation was scheduled to complete this week however the contractor canceled.

We are now looking at next week for installation.
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

The company attempted to install the letterboxes but found them too heavy to unstall without a crane.

Feedback from contractor:

"I had to cancel install for today. After our pre-install visit this morning and looking at it all, we don’t think it is safe to manually manoeuvre in this situation, as the boxes are so heavy. We have a contractor who has a crane on his truck. I will need to book him in next week.

Apologies for the cancellation."
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

08/11/2014 : New letterbox system was installed.

Note: the new letterboxes will not be in use until the fence and path have been modified.
Attachments
20141108 085017.jpg
20141108 090127.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

28/11/2014

New concrete path to letterboxes has been completed.

Note that letterboxes will not become active until signs and fencing are completed.
Attachments
20141128_124015.jpg
20141128_161453.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

15/01/2015

We have received notice that the address and no junk mail signs for the letterboxes will be installed over the next 2-3 weeks.

Once this occurs we will allow the letterboxes to be used and start the process to have the fence fixed.
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

30/01/2015

The address and junk mail signs have been installed and the letterboxes are now ready for use.

The old letterboxes will be demolished and removed after March 1st 2015.

All residents will be notified by email and a notice in the new and old mailbox.
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

Communications have been sent out advising residents to start using the new letterboxes and to make sure all mail is removed from the old letterboxes by March 1st.

Old letterboxes will be demolished as soon as the fencing around the new letterboxes has been completed.

More information on communication is available here:
/viewtopic.php?t=899
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

06/05/2015 : Fencing around the new letterboxes has been installed

The new letterboxes are now in use, the old letterboxes have been taped off.
Attachments
20150506_151547.jpg
20150516_083117.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

Tasks still to be completed (with estimated completion dates):

2015/05 : concreting around new fencing
2015/05 : demolition/cleanup of old letterbox area
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

02/06/2015 : concreting around new fencing completed
Attachments
20150605_073543.jpg
TheMews
Site Admin
Posts: 2741
Joined: Tue Jan 06, 2009 5:53 pm

Re: Installation of new letterbox system

Post by TheMews »

Demolition of old letterboxes has been completed

Note that a bottle and note was found sealed inside the old letterboxes
/viewtopic.php?t=928
Attachments
20150516_083046.jpg
20150516_083046.jpg (92.16 KiB) Viewed 45095 times
20150517_103854.jpg
20150517_103854.jpg (121.24 KiB) Viewed 45095 times
20150618_171336.jpg
20150618_171336.jpg (72.83 KiB) Viewed 45095 times
Post Reply