 Post subject: Solar Power Installation
PostPosted: Wed Aug 17, 2016 10:11 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
The Strata Company is currently investigating the benefits of installing a solar power generation system.

A solar generation system has the following benefits:

1. Reduces electricity use from the grid. Systems that use electricity during the day will use the free solar electricity generated rather than using electricity from the grid. An example of these systems are:
  • Irrigation Pump
  • Pool Pump and Chlorinator
  • Vehicle Gates
  • Security Systems (eg Cameras)


Top
   
PostPosted: Wed Aug 17, 2016 10:22 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
We have started working with several installers that specialise in solar generation to understand the costs and benefits.

The following picture shows the proposed panel location at the north/east corner of the complex:
Attachment:
TheMews_PanelLocation.JPG
TheMews_PanelLocation.JPG [ 293.74 KiB | Viewed 9882 times ]
The following chart shows the expected average daily power generation for each month of the year for 3 different solar generation systems (based on the location and elevations of the panels):
Attachment:
TheMews_SolarOutput.png
TheMews_SolarOutput.png [ 44.5 KiB | Viewed 9882 times ]


Top
   
PostPosted: Wed Oct 18, 2017 1:42 pm 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
August 2017

The strata council voted to approve the quotation provided by Infinite Energy.


Top
   
PostPosted: Wed Oct 18, 2017 1:45 pm 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
September 2017

Contractors attended the complex to inspect and gather information:
  • An electrical contractor attended site to assess the complex and discuss installation.
  • A structural engineer attended the site to inspect the roof area where the panels will be installed.

Applications were submitted:
  • Building application submitted to the City of Vincent.
  • Generation application submitted to Western Power.


Top
   
PostPosted: Wed Oct 18, 2017 1:51 pm 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
Our application to connect an embedded generation system to the grid has been approved by Western Power.


Attachments:
WesternPowerApproval.pdf [103.53 KiB]
Downloaded 390 times
Top
   
PostPosted: Thu Oct 26, 2017 2:50 pm 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
Our application to Synergy (the retailer) has been approved:


Attachments:
SynergyApplication.pdf [1.64 KiB]
Downloaded 383 times
Top
   
PostPosted: Mon Nov 06, 2017 7:53 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
Our building application to the City of Vincent has been approved.

All applications are now approved and the installation has been scheduled for November 9th.


Top
   
PostPosted: Tue Nov 07, 2017 10:23 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
Final panel layout


Attachments:
image013.jpg
image013.jpg [ 39.74 KiB | Viewed 9634 times ]
Top
   
PostPosted: Fri Nov 10, 2017 6:49 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
09/11/2017: Solar panels have been installed

Remaining tasks:
- Inverter installed and connected to panels.
- Inverter connected to power supply.


Attachments:
20171109_135106.jpg
20171109_135106.jpg [ 473.79 KiB | Viewed 9625 times ]
20171109_135915.jpg
20171109_135915.jpg [ 470.46 KiB | Viewed 9625 times ]
Top
   
PostPosted: Fri Nov 10, 2017 11:54 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
10/11/2017: Installation Completed


Attachments:
20171110_114626.jpg
20171110_114626.jpg [ 513.3 KiB | Viewed 9613 times ]
20171110_151503.jpg
20171110_151503.jpg [ 209.92 KiB | Viewed 9613 times ]
Top
   
PostPosted: Fri Nov 10, 2017 11:55 am 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
Generation and usage information is available by clicking the link below:

/solar


Top
   
PostPosted: Fri Feb 02, 2018 12:17 pm 
Site Admin

Joined: Tue Jan 06, 2009 5:53 pm
Posts: 2701
The system has now been operational for just under 3 months and is already leading to significant savings.

There savings can be seen on the power bills: /powerbills


Attachments:
savings.png
savings.png [ 9.61 KiB | Viewed 9359 times ]
Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 12 posts ] 

All times are UTC+08:00


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Limited