Author: | TheMews [ Wed May 11, 2011 3:46 pm ] | ||
Post subject: | Gas HWS Compliance (as required by regulator) | ||
The property has been inspected by the statge regulator (WA Gas Networks / Energy Safety). As a result of this inspection rectification works are required in several areas. Attachment: 20110509_WAGas_Inspection01.jpg [ 191.76 KiB | Viewed 8988 times ] Attachment: 20110509_WAGas_Inspection02.jpg [ 371.4 KiB | Viewed 8988 times ]
|
Author: | TheMews [ Thu May 19, 2011 3:16 pm ] |
Post subject: | Re: Gas HWS Compliance - Duct Doors |
Rear buildings only: Vents in duct doors have been increased as required. |
Author: | TheMews [ Mon Jun 13, 2011 7:33 am ] |
Post subject: | Re: Gas HWS Compliance - Duct Doors |
Front buildings only: Vents in duct doors have been increased as required. All duct doors have now been modified as required. |
Author: | TheMews [ Thu Jul 07, 2011 2:05 pm ] | ||
Post subject: | Re: Gas HWS Compliance - Proposed Flueing Solution | ||
Proposed flue solution to support 3 instantaneous gas heaters per duct. Option 1 - Single Flue (maximum section size 200mm) Option 2 - Double Flue (maximum section size 150mm)
|
Author: | TheMews [ Wed Nov 28, 2012 9:58 pm ] |
Post subject: | Re: Gas HWS Compliance - 38% Complete |
Progress: 38% Complete Units 01/19/37 Completed Nov 2011 (1 x ARP) Units 02/20/38 Completed Nov 2011 (1 x ARP) Units 04/22/40 Completed July 2012 Units 08/26/44 Completed Nov 2011 (2 x ARP) Units 11/29/47 Completed Oct 2011 (2 X ARP) Units 13/31/49 Completed July 2012 Units 17/35/53 Completed Sep 2012 Units 03/21/39 to be done Oct 2012 (1 x ARP) need approval to replace electric in 21 (leave capped off flue connection for future) Units 05/23/41 to be done Oct 2012 (1 x ARP) still awaiting approval from ownerof5 (leave capped off flue connection for future) Units 07/25/43 to be done Dec 2012 (1 x ARP) Units 12/30/48 to be done Dec 2012 (1 x ARP) Units 14/32/50 to be done Dec 2012 (1 x ARP) owner14 and 32 now agree to replace as doing others(inv to exclusive) Units 16/34/52 to be done Dec 2012 (1 x ARP)52 added to ARP list Units 06/24/42 scheduled for 2013 Units 09/27/45 scheduled for 2013 Units 10/28/46 scheduled for 2013 Units 15/33/51 scheduled for 2013 Units 18/36/54 scheduled for 2013 |
Author: | TheMews [ Tue Jan 15, 2013 2:30 pm ] |
Post subject: | Re: Gas HWS Compliance - 44% complete |
Progress: 44% Complete Units 01/19/37 Completed Nov 2012 Units 02/20/38 Completed Nov 2012 Units 04/22/40 Completed July 2012 Units 05/23/41 Completed Dec 2012 Units 08/26/44 Completed Nov 2012 Units 11/29/47 Completed Oct 2012 Units 13/31/49 Completed July 2012 Units 17/35/53 Completed Sep 2012 Units 03/21/39 scheduled for 2013 Units 06/24/42 scheduled for 2013 Units 07/25/43 scheduled for 2013 Units 09/27/45 scheduled for 2013 Units 10/28/46 scheduled for 2013 Units 12/30/48 scheduled for 2013 Units 14/32/50 scheduled for 2013 Units 15/33/51 scheduled for 2013 Units 16/34/52 scheduled for 2013 Units 18/36/54 scheduled for 2013 |
Author: | TheMews [ Fri Mar 15, 2013 2:08 pm ] |
Post subject: | Re: Gas HWS Compliance - 77% complete |
Progress: 77% Complete Units 01/19/37 Completed Nov 2012 Units 02/20/38 Completed Nov 2012 Units 03/21/39 Completed Jan 2013 Units 04/22/40 Completed July 2012 Units 05/23/41 Completed Dec 2012 Units 06/24/42 Completed Feb 2013 Units 07/25/43 Completed Jan 2013 Units 08/26/44 Completed Nov 2012 Units 09/27/45 Completed Mar 2013 Units 11/29/47 Completed Oct 2012 Units 12/30/48 Completed Jan 2013 Units 13/31/49 Completed July 2012 Units 16/34/52 Completed Feb 2013 Units 17/35/53 Completed Sep 2012 Units 10/28/46 scheduled for 2013 Units 14/32/50 scheduled for 2013 Units 15/33/51 scheduled for 2013 Units 18/36/54 scheduled for 2013 |
Author: | TheMews [ Tue Jun 18, 2013 11:03 am ] |
Post subject: | Re: Gas HWS Compliance - 83% complete |
Progress: 83% Complete Units 01/19/37 Completed Nov 2012 Units 02/20/38 Completed Nov 2012 Units 03/21/39 Completed Jan 2013 Units 04/22/40 Completed July 2012 Units 05/23/41 Completed Dec 2012 Units 06/24/42 Completed Feb 2013 Units 07/25/43 Completed Jan 2013 Units 08/26/44 Completed Nov 2012 Units 09/27/45 Completed Mar 2013 Units 11/29/47 Completed Oct 2012 Units 12/30/48 Completed Jan 2013 Units 13/31/49 Completed Jul 2012 Units 15/33/51 Completed Apr 2013 Units 16/34/52 Completed Feb 2013 Units 17/35/53 Completed Sep 2012 Units 10/28/46 scheduled for 2013 Units 14/32/50 scheduled for 2013 Units 18/36/54 scheduled for 2013 |
Author: | TheMews [ Thu Aug 08, 2013 11:35 am ] |
Post subject: | Re: Gas HWS Compliance - 100% Complete |
Progress: 100% Complete Units 01/19/37 Completed Nov 2012 Units 02/20/38 Completed Nov 2012 Units 03/21/39 Completed Jan 2013 Units 04/22/40 Completed July 2012 Units 05/23/41 Completed Dec 2012 Units 06/24/42 Completed Feb 2013 Units 07/25/43 Completed Jan 2013 Units 08/26/44 Completed Nov 2012 Units 09/27/45 Completed Mar 2013 Units 10/28/46 Completed Jul 2013 Units 11/29/47 Completed Oct 2012 Units 12/30/48 Completed Jan 2013 Units 13/31/49 Completed Jul 2012 Units 14/32/50 Completed Jul 2013 Units 15/33/51 Completed Apr 2013 Units 16/34/52 Completed Feb 2013 Units 17/35/53 Completed Sep 2012 Units 18/36/54 Completed June 2013 |